Hello Axel,
thanks for your feedback. Obviously there is no cost transfer from Solution Manager to PPM, but there is a time transfer. You can record time on an RfC and on Change Documents in Solution Manager and link that RfC to a task in PPM. The time will be transferred (asynchronous batch-job) to PPM. There you can calculate actual cost based on actual time needed and link the PPM-task to a cost object for charging.
According to my understanding, that should work. At the moment I have difficultiers with the batch-job: I'm getting an error, when I try to execute DPR_CATS_CPR_TRANSF --> "Time confirmation is not allowed for the project type" Does anyone have a clue, how to allow time confirmation for a project type? Unfortunately, I don't have much PPM-experience, yet...
Thanks, Patric