Availability check - Planned order not considered

$
0
0

Hi Experts,

 

I am facing an issue in Make to Order scenario.

 

 

My sale order is of quantity 10.

 

when i save the sale order, i get confirmed quantity as Zero.

 

But in my controls setting of availability check i have selected consider all firmed planned order.

 

Now  i have a firmed planned order for this sale order.

 

but still system shows confirm quantity as Zero.

 

 

 

Let me know what is the correct procedure and whether planned orders are considered for availabilty check for MTO scenario or not.

 

 

Regards,

Birendra